Question: Can you help me to create; 1- Create a risk register, including - List of all risk - List of potential responses - Root causes

Can you help me to create;

1- Create a risk register, including

- List of all risk

- List of potential responses

- Root causes of risk

2- Prioritize risks

Problem Case Summary

Wilmonts is a top-ranked US retail pharmacy with more than 8,000 stores nationwide. The company is secretly considering delivering prescriptions by flying drone. DroneTech, a small firm in San Francisco, CA announced the approach in March, and Wilmonts has made an agreement with DroneTech to prototype this project in the San Francisco area. DroneTech will provide the drone technology as well as the drone piloting and delivery systems, but will customize its systems and business process to conform to Wilmonts requirements. You are the project manager assigned to lead this project. (Depending upon the course domain, the case positions the student as the project manager in either Wilmonts IT, Wilmonts Pharmacy Operations, or DroneTech Engineering.)

Wilmonts has limited the project expenditures to a maximum of US$1,750,000 for this prototype project and will implement it first in only four stores.

The project begins next January 5 and the first customer delivery flight should take place no later than November 30 to avoid harsh weather in the San Francisco area.

You will need to plan tasks and assign team members to them from a list of people involved in the project. Regular meetings need to be held with the team and stakeholders as well as other forms of communication.

Approval points are needed through the project sequence.

Risks, testing, quality control and provision issues may develop.

Issues in security, reliability, integrity, interfaces between the systems of the two organizations and customer interaction are all considerations that must be made as you plan the project.

User training and other preparations will be required for system implementation. The Wilmonts Change Management Team will assist you in this effort.

CASE PROBLEM Part 1:

Wilmonts is a top-ranked US retail pharmacy company based in St. Louis, MO with more than 8,000 stores nationwide and in all 50 states, and employing more than 244,000 people overall. The company has engaged in a number of innovative business practices, and now they are once again secretly considering breaking ground with an even newer concept delivering prescriptions and drugstore items by flying drone.

The concept isnt new a small firm named DroneTech in San Francisco announced the approach in March, and they are looking to develop a relationship with drugstores nationwide to launch the concept for real. Wilmonts may be the big break they are looking for!

The Operations Vice President (George Cranston) of Wilmonts wants to develop a pilot project to get something moving and see how this works. George will provide the funds and will oversee all aspects of this initiative. You are the Project Manager on Wilmonts business operations side who will manage the project generally for Mr. Cranston.

Mr. Cranston has made an agreement with DroneTech CEO and founder Jordan Kempler to prototype this project in the San Francisco area, which is the home location of the DroneTech organization where it developed the system. DroneTech will customize its systems, interfaces and business process to conform to project requirements from Wilmonts. Mary Pearson is the Project Manager for Wilmonts internal IT department, and she has been assigned by CIO, James Connor, to lead the information systems development that will be needed to support the initiative. Phillip Greenberg is the project manager at DroneTech who will work with you. Generally, from the Operations perspective, the project will likely need to accomplish the following:

Develop a Wilmonts online order entry process that will allow customers in the San Francisco area to register their willingness to have a drone deliver their orders by means of online entry or smartphone entry. There will be significant restrictions on the approval of customers for this service, so there will need to be a segment of the process to allow. Wilmonts management to approve the customer, send a confirmation to the customer, etc.

Create reports for Wilmonts management to provide information on sales, customer reactions and key performance indicators that senior management will define for you.

Create communications for customers electronically through email, online and through mobile alerts as the customer requests.

DroneTech will handle piloting the drones and delivery of the products. They already have processes that handle order entry, delivery confirmation and a mobile app, but they need to be customized for Wilmonts so that customers dont see these as two separate companies. Eileen Seymour is the point of contact on the information systems side with DroneTech and will be overseeing the team on their side. A price for this system customization is not yet determined and the development of this proposal will be a part of your project plan. You will need to build in the contract negotiations between Wilmonts and DroneTech as you develop the project plan as well. Members of the legal teams of both organizations will assist you with this.

Ensure that the relationship between DroneTech and Wilmonts does not compromise the security of Wilmonts business information, the customers privacy and the proprietary information about how Wilmonts will use the drones for delivery. You will work with Wilmonts Information Security Management Team to accomplish this, and William Scott is the project lead on that team for this project.

You will need to identify basic business process requirements and then determine your team members from the list of people given in this document as you move toward final project planning.

It has been determined that only four (4) Wilmonts pharmacies will participate in the prototype delivery system. These are in a close geographic area to one another, and they are in a non-city environment consisting mainly of suburban homes and small businesses. Customers in apartment buildings will not be permitted in the prototype due to delivery issues. You will need to ensure that the four participating pharmacies are fully ready to engage in this prototype by the time for first flight, and the drone deliveries need to be seamless enhancements to Wilmonts already top-quality delivery processes for customers.

The IT folks have determined that no additional IT infrastructure will be required for this project from Wilmonts, as all of that specialized technology is only on the DroneTech side, and they will be including it in their proposal and a separate project plan that they will give to you as a part of their contract. Wilmonts can accommodate operating this prototype system within their existing infrastructure that handles customer orders, but those processes need to be enhanced in order to provide this delivery option and all the management processes that must accompany them.

Wilmonts has allocated a maximum of $1,750,000 for this prototype project, although this is only an ultimate constraint you will eventually need to tell Mr. Cranston what your project estimate will be, but you dont have enough information about the project design yet to be able to give such a budget figure. You have been asked by Mr. Cranston to ensure that your project not only does not go over this figure, but that it is under that total if possible. The two companies agreed that they would like to begin the project on next January 5, and that their first customer delivery flight should take place no later than November 30 to avoid harsh weather in the San Francisco area. Of course, you also need to include specific steps and processes for:

Regular Meetings with the Team, Stakeholders, and Cross-impacted areas of the company.

Approval points as needed through the project sequence.

Points at which you will refine cost and staffing requirements (you do not need to calculate costs or total staffing at this point)

Points at which you will produce the various Project Plan documentation deliverables discussed in class.

Testing, quality control and provision for issues that may develop.

User training and other preparations for system implementation. The Wilmonts Change Management Team, headed by Shirley Johnson, will assist you in this effort.

Can you help me to create; 1- Create a risk register, including- List of all risk - List of potential responses - Rootcauses of risk 2- Prioritize risks Problem Case Summary Wilmonts is a

Summary of Personnel Involved in the Project (name initials are in brackets):

DroneTech Corporation Staff:

Jordan Kempler (JXK), CEO and Founder

Phillip Greenberg (PAG), Project Manager main point of contact

Stephanie Williams (SMW), Senior Business Analyst

Gerald Hasper (GPH), Flight Operations Manager

Eileen Seymour (ERS), Project Lead, IT Systems

Katie ORyan (KRO), Corporate Attorney DroneTech Wilmonts Staff:

George Cranston (GWC), Operations VP

James Connor (JFC), CIO

Mary Pearson (MJP), Project Lead, IT Systems Team

William Scott (WKS), Project Lead, Security Team

Julie Green (JRG) Pharmacy Manager Store #35864

Steve Haskell (SLH) Pharmacy Manager Store #32185

James ODonnell (JLO) Pharmacy Manager Store #38734

Wilma Marcy (WPM) Pharmacy Manager Store #33001

You as Project Manager on the Business Operations side (Come up with your own initials)

Mary Kerstner (MJK), Business Systems Analyst

Jonathan Perry (JSP), Retail Operations Assistant

William Postner (WKP), Marketing Analyst

Sherry Loganthorpe (SPL), Social Media Specialist

Linda Thornton (LET), Online Customer Process Analyst

Gerald Peritoni (GEP), Testing Specialist

Elizabeth Walton (EMW), Senior Testing Specialist

Shirley Johnson (SPJ), Change Management Coordinator

Alan Swanson (AES), Attorney Legal Department

Denise Delgado (DLD), Financial Operations

Part 2: Additional Information for Part 2: Please review the Part 1 Case Problem information as it is the general background and requirements of the case. This information should be added to the following clarifications regarding the project schedule:

1. Total Project Cost must not exceed Project Constraints. Project Schedule should begin January 5, and should meet the schedule constraints as per the case for completion, etc. You may assume 100% (1.0FTE) allocation to this project for each resource in the list below. Load leveling is NOT required for this assignment, and over-allocation warnings on your WBS will not be counted as a problem as long as the resource effort allocation is reasonable.

Do not include things like "procurement management plan" or "staffing plan" or "quality management plan" as these are not a part of this case problem. A generic WBS is not acceptable for this assignment. This is practice for you to see how you might deliver such a detailed schedule for this case problem to your boss, and it will be evaluated that way. 3. It is up to you to add the project management, communication, testing and training tasks as needed to make the project successful. Use the information in the case and the other assignments, along with your own ideas about how much effort is involved to ensure a quality implementation overall throughout the project. Be sure that you do not exceed the project constraints. 4. Remember that this project will be tight in terms of time and cost, so do not include steps that are not really necessary for this particular project. You should schedule the project from the beginning, including Charter/Scope, planning meetings, Risk Management and Communication Plan development, WBS and schedule development these items need to appear in this schedule along with resource assignments and the appropriate costs that go along with them. 5. Finally, you are required to indicate an appropriate quantity of tasks that have likely been already in progress or completed. Assume that we are looking at your schedule on June 27. Show which work packages would probably be at what stage of completion by this specific time in the schedule. Use your own judgment based on the work package finish dates, but be reasonable! 6. The personnel involved in the DroneTech Corporation do not have billing rates per hour because their cost is being absorbed by the fixed fee specified in their proposal below. These people should be listed in your resource sheet, but with $0.00 standard rate, and they should be assigned to the appropriate tasks for the project. *. Jordan Kempler (JXK) - CEO and Founder * Phillip Greenberg (PAG) - Project Manager - main point of contact *. Stephanie Williams (SMW) - Senior Business Analyst * Gerald Hasper (GPH) - Flight Operations Manager * Eileen Seymour (ERS) - Project Lead, IT Systems * Katie Q'Ryan (KRO) - Corporate Attorney - DroneTech They should be assigned to project tasks as appropriate using the information in the case and the details below. 7. DroneTech Corporation Contract Fees and Dates: After a complicated negotiation, Wilmont's has signed a contract with DroneTech specifying the following phased payment plan that is linked to specific dates or deliverables. You are responsible for ensuring that the payments occur on time, but are only made if the appropriate conditions have been met. Be sure to include the necessary tasks in your WBS to accommodate evaluating, and paying for, these contract activities: * Total DroneTech fee for customizing order entry, delivery confirmation and mobile application software to Wilmont's' specifications: $423,592.00 with payments to be received as follows: A. February 2 - Initial payment due: $42,000 \& After Wilmont's approval of DroneTech Customization Design Phase: Payment of $45,000 * After Successful demonstration of Order Entry module: Payment of $35,000 - After Successful demonstration of Delivery Confirmation module: Payment of $55,000 *. After Successful demonstration of Mobile Application module: Payment of $25,000 * After Production System Test Approval by Wilmont's: Payment of $85,000 * After Successful Implementation Signoff by Wilmont's: Final Payment of $136,592 8. Wilmont's Staff, Internal effective hourly rates and official abbreviated names (initials): * George Cranston (GWC), Operations VP (\$200/hr) \&. James Connor (JFC), ClO (\$150/hr) * Mary Pearson (MJP), Project Lead, IT Systems Team (\$55/hr) * William Scott (WKS), Project Lead, Security Team (\$50/hr) * Julie Green (JRG) Pharmacy Manager Store \#35864 (\$60/hr) * Steve Haskell (SLH) Pharmacy Manager Store \#32185 (\$60/hr) * James O'Donnell (JLO) Pharmacy Manager Store \#38734 (\$60/hr) * Wilma Marcy (WPM) Pharmacy Manager Store \#33001 (\$60/hr) - You as Project Manager on the Business Operations side (Come up with your own initials) (\$55/hr) *. Mary Kerstner (MJK), Business Systems Analyst (\$45/hr) * Jonathan Perry (JSP), Retail Operations Assistant (\$40/hr) * William Postner (WKP), Marketing Analyst (\$52/hr) * Sherry Loganthorpe (SPL), Social Media Specialist (\$45/hr) * Linda Thornton (LET), Online Customer Process Analyst (\$40/hr) * Gerald Peritoni (GEP), Testing Specialist (\$38/hr) * Elizabeth Walton (EMW), Senior Testing Specialist (\$49/hr) * Shirley Johnson (SPJ), Change Management Coordinator (\$40/hr) *. Alan Swanson (AES), Attorney - Legal Department (\$60/hr) * Denise Delgado (DLD), Financial Operations Analyst (\$40/hr) 9. The following is the estimated total EFFORT HOURS for only the business process enhancements and reporting to the customer and Wilmont's management for the prototype systems. (these do not include the time for process design requirements, project management activities, testing, training, final implementation or meetings - you will need to add those additional steps and estimates for each): 1. Wilmont's/DroneTech Legal Contract Negotiations ( 250 hours) 2. Wilmont's Inventory Management Process Modifications ( 180 hours) 3. Wilmont's Pharmacy Customer Information Modifications (180 hours) 4. DroneTech Reporting Interface - Wilmont's Side System (150 hours) 5. Website/Mobile App Content Update - Wilmont's Side (175 hours) 6. Social Media Strategy and Implementation Plan - (75 hours) 7. Customer/Management Reporting (135 hours) 8. Store Management Reporting (135 hours) 9. Credit Card Processing (75 hours) 10. Wilmont's Sales Management Reporting (150 hours) You need to determine who on Wilmont's and DroneTech's staff should be involved in the various deliverables based upon what you think best, and how their positions and skills relate to the tasks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!