Question: can you help me wirh this question please Question 7 1 pts 5- Draw the activity-on-node project network associated with the following activities for a
can you help me wirh this question please
Question 7 1 pts 5- Draw the activity-on-node project network associated with the following activities for a construction project. How long should it take the team to complete this project? What are the critical path activities? Provide your answers in the blank fields below. Immediate Predecessor(s) Time (Days) Activity IA 3 B A 4 IC A 6 D B 6 E B 4 IF c 4 G D 6 H EF 8 Critical Path: (separate nodes in your path with "-") Project Completion Time: days DOO 000 Ft 0 II 4) FS F7 F8 19 FO FIL F12 * + $ 4 % 5 & 7 ) 0 6 8 9 { R. Y U O P