Question: Can you please help wit this HW question? Completion time (from start to finish) of a building remodeling project is normally distributed with a mean
Can you please help wit this HW question?
Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 workdays and a standard deviation of 10 workdays. To be 99% sure that you will not be late in completing the project, you should request a completion time of _______ workdays.
Question 8 options:
1)
211
2)
207
3)
223
4)
200
5)
250