Question: can you please show work step by step Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $5.6 million. After
Smithson Mining operates a silver mine in Nevada. Acquisition, exploration, and development costs totaled $5.6 million. After the silver is extracted in approximately five years, Smithson is obligated to restore the land to its original condition, including constructing a wildlife preserve. The company's controller has provided the following three cash flow possibilities for the restoration costs: (1) $500.000, 20% probability: (2) $550,000, 45% probability; and (3) $650,000, 35% probability. The company's credit- adjusted, risk-free rate of interest is 6%. What is the initial cost of the silver mine? Show work, including present value calculations. If using a table, cirs table and attach