Question: Can you please Solve this in under 30 mins please. Can you please Solve this in under 30 mins please. Question 11 Not yet answered
Can you please Solve this in under 30 mins please.

Can you please Solve this in under 30 mins please.
Question 11 Not yet answered Marked out of 1 P Flag question Computing the EF of the activity is done directly on the tables without referring to the AOA sketch Select one: O True O False Question 12 Not yet answered Marked out of 1 p Flag question The EF and LF for the critical activities are not necessarily equal Select one: O True O False Question 13 Not yet answered Marked out of 1 p Flag question If the total float = 0, then all other floats are zero Select one: O True O FalseStep by Step Solution