Question: Canada Initiating involves developing a project charter, which is a part of the project management knowledge area. a . risk b . communication c .
Canada
Initiating involves developing a project charter, which is a part of the
project
management knowledge area.
a risk
b communication
c scope
d integration
Which of the following items is NOT included in the Project Charter?
a A Gantt chart
b The name of the project manager
c Project information
d Stakeholder signatures
A work breakdown structure, project schedule, and cost estimates are outputs of the
process.
a closing
b executing
c planning
d initiating
A document that formally recognizes the existence of the project and provides direction
on the project's objectives and management is known as
a Project Charter
b PM Plan
c Contract
d Business Case
Which of the following outputs is often completed before initiating a project?
a project charter
b kickoff meeting
c business case
d stakeholder register
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock