Question: Cans are made in a process with two resources. The first resource has a capacity of 2 . 3 cans per second. The capacity of

Cans are made in a process with two resources. The first resource has a capacity of2.3 cans per second. The capacity of the second resource is 2.1 cans per second. The first resource has 1 worker and the second resource has 9 workers.What is the capacity of the process if workers can now work at both resources and processing times do not change?Note: Do not round intermediate calculations. Round your answer to 3 decimal places.Capacity of cans per second