Question: Capacity Planning Question Two products A and B share the same machine capacity. Current planning information is shown below: Product A Product B Demand forecast
| Capacity Planning Question | |||||
| Two products A and B share the same machine capacity. Current planning information is shown below: | |||||
| Product A | Product B | ||||
| Demand forecast (units / year) | 9800 | 4700 | |||
| Batch size (units / batch) | 200 | 100 | |||
| Standard processing time (hours / unit) | 1.2 | 1.1 | |||
| Standard setup time (hours / batch) | 2.0 | 3.0 | |||
| The company works 300 days per year and operates 2 shifts each day, each shift covering 8 hours per day. | |||||
| We desire a 15 percent capacity cushion | |||||
| Using the information provided, how many machines are needed if we desire a 15% capacity cushion? | |||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!