Question: Capacity problem -8 points In a manufacturing scenario, you work five (5) days, seven (7) hours per shift in 2 manufacturing shifts given 10,000 units
- Capacity problem -8 points
In a manufacturing scenario, you work five (5) days, seven (7) hours per shift in 2 manufacturing shifts given 10,000 units per hour.
- Find available time or designed capacity.
- If weekly production is 10,000 units, find % utilization.
- If the effective capacity is 95% find % efficiency
- In a scenario of an actual production of 20,000 units and a % utilization of 80%, find designed capacity.