Question: CAPITAL BUDGETING PROBLEMS Question Answer (Show work for full & any partial credit) Problem #1: Which machine? Why? Problem #2: Which machine? Why? Problem #3:
CAPITAL BUDGETING PROBLEMS
| Question | Answer (Show work for full & any partial credit)
|
|
|
|
|
| Payback: Discounted Payback: IRR: MIRR: NPV
|
Problem #1
Company needs to decide between two machines.
Machine A costs 10,000 and produce after tax cash flows of 3,000 per year for 5 years. No salvage.
Machine B costs 18,000 and produce after tax cash flows of 2,800 per year for 10 years. No salvage.
Discount rate is 8%
Which machine would you recommend?
Problem #2
Company needs to decide between two machines.
Machine C costs 10,000 and produce after tax cash flows of 4,000 per year for 3 years. No salvage.
Machine D costs 14,000 and produce after tax cash flows of 3,000 per year for 7 years. No salvage.
Discount rate is 8%
Which machine would you recommend?
Problem #3
Calculate NPV, Payback, Discounted Payback, IRR and Modified IRR for the following project
Initial Investment: -100,000
Annual project cash flow 22,000 for 6 years
Cost of capital is 6%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
