Question: Case 1 ( 5 0 p . ) A project management problem is detailed in the table below. Times are given in weeks. Round all
Case p A project management problem is detailed in the table below. Times are given in weeks. Round all your answers to digits after the decimal point.
a p Draw the network diagram.
b p Calculate the expected time for each activity.
c p Calculate the slack time for each activity.
d p Which activities form the critical path? Why are these activities critical?
e p What is the estimated time of the critical path?
f p What is the project variance?
g
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
