Question: CASE # 1 Abbott Corp. and Hobbs Construction Co . entered into an oral contract whereby Hobbs was to build certain roads in Jackson Village.
CASE #
Abbott Corp. and Hobbs Construction Co entered into an oral contract whereby Hobbs was
to build certain roads in Jackson Village. The roads were to be built to grade stakes that
were set by Abbott engineer. Abbott continually inspected the work from day to day and at
all times had control of the elevation to which the finished roads were to be built. The
stakes were set at ft elevation intervals. Both parties knew the character of the subsoil,
both at the time of entering into the work and at the time the work was being done; each
was fully aware of the possibility that roads built on such soil might settle. The roads were
inspected during the progress of the work by a Jackson County inspector who was
principally concerned with the depth of rock and with the surfacing. The roads were
completed according to the Jackson County specifications and at the elevation set and
required by Abbott. During the course of the work, Hobbs was fearful that the roads might
settle and wanted to build them higher than the elevation set by Abbott. Hobbs advised
Abbott that the roads might settle, but Abbott would not permit Hobbs to build the roads
higher because a higher road would have required additional fill on each of the lots. Soon
after the work was complete, there was a slight settlement of some portions of the roads so
that the roads were below the ft elevation as required by Abbott. Abbott insisted that
Hobbs raise the elevation of the roads at Hobbs expense. Hobbs refused. Simultaneous with
the Jackson Village project, Hobbs had another contract with Abbott to perform identical
work on the Long Mile Estates, First Addition project. Abbott insisted that Hobbs raise the
elevation of the roads on this project at Hobbs expense, just as Abbott had insisted on the
Jackson Village project. Hobbs again refused. When Abbott said it would not accept the
work and would not pay unless Hobbs altered its performance in accordance with this
new directive, Hobbs stopped work on the project.
Questions:
If you had decision making power over this case, how would you rule?
Are Hobbs actions a form of economic duress?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
