Question: Case 2 ( questions 6 - 1 3 ) The following table shows a set of activities, their relationships with each other and duration (
Case questions
The following table shows a set of activities, their relationships with each other and duration number of
weeks for a project. Draw a network diagram showing each activity of the project. Complete the table
with the appropriate values of ES EF LS LF and slack for each activity.
What is the slack for activity A
Answer:
What is the slack for activity E
Answer:
What are LS and LF for activity B
show work clearly