Question: CASE # 3 Using the table above please indicate: a ) The expected duration for the activities # 1 & # 5 ( using PERT
CASE #
Using the table above please indicate:
a The expected duration for the activities # & #using PERT
estimation
b Which activities the project start with?
c Using duration of for activity # and suppose that the total duration
of the project is What is the Latest Time to finish and to start for
the direct preceding activities of activity #
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock