Question: CASE # 3 You are tasked with managing the construction of a new bridge over a river. The project involves several critical activities that must

CASE # 3
You are tasked with managing the construction of a new bridge over a river. The project involves several critical activities that must be completed in a timely manner to ensure the successful completion of the bridge. Below is a list of activities along with their respective durations and dependencies:
Activity: A Description: Site Preparation Duration: 10 days Predecessors: None
Activity: B Description: Foundation Construction Duration: 20 days Predecessors: A
Activity: C Description: Pier Construction Duration: 30 days
Predecessors: B
Activity: D Description: Deck Construction Duration: 25 days
Predecessors: C
Activity: E Description: Railings Installation Duration: 15 days Predecessors: D
Activity: F Description: Final Inspection Duration: 5 days
Predecessors: E
Using the Critical Path Method (CPM) or Program Evaluation and Review Technique (PERT), answer the following questions:
Construct the activity network for this project - include EST, EFT, LST and LFT in your diagram
Determine the slack and float for each activity
Determine critical path for this project.
Calculate the total duration of the project.
Identify any non-critical paths and their durations.
If Activity B is delayed by 5 days due to unforeseen circumstances, how will it impact the project timeline?
Recalculate the critical path and total duration accordingly.
Note: You may assume that all activities can be started as soon as their predecessors are completed and that there are no resource constraints.
 CASE # 3 You are tasked with managing the construction of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!