Question: Case 6 - 2 ase 6 . 2 Shoreline Stadium Case ASSIGNMENT Given the information provided in Table 6 . 3 , construct a network

Case 6-2ase 6.2
Shoreline Stadium Case
ASSIGNMENT
Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:
1. Will the project be able to be completed by the April 3 deadline? How long will it take?
2. What is the critical path for the project?
3. Based on the schedule would you recommend that G&E pursue this contact? Why?
Include a one-page Gantt chart for the stadium schedule.
Shoreline Stadium Case
ID Activity Duration Predecessor(s)
1 Baseball Stadium
2 Clear stadium site 70 days
3 Demolish building 30 days 2
4 Set up construction site 70 days 3
5 Drive support piling 120 days 4
6 Pour lower concrete bowl 120 days 5
7 Pour main concourse 120 days 6
8 Install playing field 90 days 6
9 Construct upper steel bowl 120 days 6
10 Install seats 140 days 9
11 Build luxury boxes 90 days 9
12 Install jumbotron 30 days 9
13 Stadium infrastructure 120 days 9
14 Construct steel canopy 75 days 10
15 Light installation 30 days 10
16 Build roof supports 90 days 4
17 Construct roof 180 days 16
18 Install roof tracks 90 days 14
19 Install roof 90 days 17,18
20 Inspection 20 days 8,11,13,15,19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!