Question: Case 6 - 2 ase 6 . 2 Shoreline Stadium Case ASSIGNMENT Given the information provided in Table 6 . 3 , construct a network
Case ase
Shoreline Stadium Case
ASSIGNMENT
Given the information provided in Table construct a network schedule for the stadium project and answer the following questions:
Will the project be able to be completed by the April deadline? How long will it take?
What is the critical path for the project?
Based on the schedule would you recommend that G&E pursue this contact? Why?
Include a onepage Gantt chart for the stadium schedule.
Shoreline Stadium Case
ID Activity Duration Predecessors
Baseball Stadium
Clear stadium site days
Demolish building days
Set up construction site days
Drive support piling days
Pour lower concrete bowl days
Pour main concourse days
Install playing field days
Construct upper steel bowl days
Install seats days
Build luxury boxes days
Install jumbotron days
Stadium infrastructure days
Construct steel canopy days
Light installation days
Build roof supports days
Construct roof days
Install roof tracks days
Install roof days
Inspection days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
