Question: Case # 7 Chubb a large software development company entered into an agreement with a general contractor to build a simple 5 0 , 0
Case #
Chubb a large software development company entered into an agreement with a general
contractor to build a simple square foot office building with an open office concept. The
architect hired by Chubb questioned the three estimate line items in the contractor's guaranteed
maximum price proposal, which appeared to be heavy. Columbia Construction the contractor
responded that these costs may be needed and the owner will receive of any savings,
according to the terms of the contract. The contractor did not manage the project efficiently and
finished four months late. Because of this delay, the contractor reported that they overran the
bottomline GMP and there were not any savings to share. If a contractor mismanages the
work, does the owner lose an opportunity for savings? The architect closely monitored the
work involved with the three subject estimate items and was confident that the contractor
underran the estimate in these areas. The contractor indicated that it was not a "line item
guaranteed maximum price estimate, but rather only the bottom line was what was
guaranteed."
Questions:
NOTE: Explain Your Answers in Detail.
Think Outside the box ie subsequent damages, countersuits
If there were savings on single line items, especially ones that were questioned early,
can the contractor use these savings to offset overruns in other areas? Is this legal?
Will an audit now help either party?
What do standard contracts say?
Lastly, if a contractor mismanages the work, does the owner lose an opportunity for
savings? What are the legal ramifications or considerations?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
