Question: Case 9 . 6 Construction project network diagram. The Now Wedding Please complete CASE 9 . 6 The Now Wedding Project Part A and CASE
Case Construction project network diagram.
The Now Wedding
Please complete CASE The Now Wedding Project Part A and CASE Part B to finish your project page
PART A Questions:
Develop a project network for the Now wedding, include activity, description, durations and predecessor. Determine critical path as well.
Create a schedule for the wedding using MS Project. Can you reach the deadline of January for the Now wedding? If you cannot, what would it cost to make the January deadline and which activities would you change?
PART B Questions:
Several complications arose during the course of trying to meet the deadline of January for the Now Wedding rehearsal. Since Lauren was adamant on having the wedding on January as was Connor for obvious reasons the implications of each of these complications had to be assessed.
On January the chairman of the Vestry Committee of the church was left unimpressed by the added donation and said he wouldnt reduce the notice period from to days.
Mother comes down with the day flu as she starts work on the guest list on January
Bobs Printing Shop press was down for day on January in order to replace faulty brushes in the electric motor.
The lace and dress material were lost in transit. Notice of the loss is received on January
Can the wedding still take place on January If not, what options are available?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock