Question: CASE STUDY. GRAYSTON DRIVE PEDESTRIAN BRIDGE COLLAPSE In October 2015 a pedestrian bridge off Grayston drive collapsed, killing two and injuring 23 people. The bridge
CASE STUDY. GRAYSTON DRIVE PEDESTRIAN BRIDGE COLLAPSE
In October 2015 a pedestrian bridge off Grayston drive collapsed, killing two and injuring 23 people. The bridge under construction was intended as a pedestrian and cyclist bridge crossing over the M1 between Alexandra and Sandton, Johannesburg for a safer and quicker route for approximately 10 000 people. Murray and Roberts (M&R) were the contractors appointed to construct and oversee the bridge construction. Murray and Roberts witnesses indicated that the collapse was a result of strong winds on that day; and they also claimed that the form-scaff design was inadequate. A Murray and Roberts spokesperson indicated that the form-scaff had not provided documentation with the sequence since the construction was standard practice; and that that Murray and Roberts was concerned that the design and drawings might not have been effectively communicated.
2.2 Discuss the important aspects of interviewing that the Murray and Roberts investigator should consider. (10)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts