Question: Case Study Overview: New Energy, Inc. is a fast - growing supplier of green energy solutions, including wind turbines, solar technology, etc. Their growing sales
Case Study
Overview: New Energy, Inc. is a fastgrowing supplier of "green" energy solutions, including wind
turbines, solar technology, etc. Their growing sales force and varying sales commission plans
prompted the need for a centralized and automated commission system to replace their spreadsheet
intensive procedures.
Project: Don is the head of Accounting and approved the project plan developed by the assigned
project manager, Mary. Their preliminary research showed that a software package was the most cost
effective solution. Mary's scope statement included these project objectives:
o Research and produce a list of the three packages that best fit the company's need.
o Facilitate a decision for the best package to obtain o Procure the package.
o Install the package.
Progress: It took months to research and find the three packages. Selecting the package was
contentious. The Sales department wanted a webbased solution, which the VP of sales, Chris, said
would be easiest for the salespeople to use.
Accounting wanted a product that had tighter security and was easier to customize. Since the system
was being paid for with Accounting's budget, Don prevailed.
Issue : Once the software contract was signed, Don became busy and largely left the installation to
Mary and the technical team. Don wanted the project completed by a fixed date, and Mary felt
pressured to get installation done without much requirements analysis, especially given she had only
one systems analyst, Bob, on the project.
Issue : Bob focused his time on converting the spreadsheet data to the new system, and on
customizing the many new user interfaces available. He conducted extensive interviews of key staff to
learn their needs for the interfaces. As Bob was interviewing, Chris requested that the most common
sales interface be duplicated as a web page, and Bob agreed because it was easy. While they were at it
Bob showed Chris a nifty Flash component for the page, which Chris loved, and it was added as a
requirement.
Issue : During the package installation, Sales announced the addition of a new product line with an
entirely different commission structure. Don held a meeting and informed the team that the new
commission plan had to be incorporated into the project and that the deadline could not slip.
Issue : During installation, Bill, a developer, and the Accounts Payable lead, Allison, discovered that
the project scope did not include changes to other systems like General Ledger GL Bill said he
could code something quickly and that this would save Allison's team many hours every payroll. He
was ahead of schedule, so Mary agreed. Unfortunately, it took longer to code and test than Bill
thought, and consequently he didn't finish testing all of the exceptions for the new commission system.
The package was implemented on schedule, but with several problems due to some exceptions not
working correctly. There were other problems with bad data and incorrect reports. Don was not happy.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock