Question: CASE STUDY THREE A ROCKY SITUATION ( Report required ) Party 1 : General Contractor Peart Construction, Inc. ( Peart ) Party 2 : Subcontractor

CASE STUDY THREE A ROCKY SITUATION (Report required)
Party 1: General Contractor Peart Construction, Inc. (Peart)
Party 2: Subcontractor Bonham Construction, LLC (Bonham)
Party 3: Second Tier Subcontractor Hawkins Dirtworks, LLC (Hawkins)
Project: Wind Farm Substation Private Commercial
On June 3,2012, Gadd Wind Energy, LLC (Gadd), and Peart entered into a
written contract under the terms of which Peart was to construct for Gadd a substation to
be used in connection with an existing wind farm located in Southwest Oklahoma. Peart,
in turn, proposed a written, lump-sum subcontract to Bonham for the sitework, which
included, in part, mass excavation and fill operations. The subcontract contained the
following provision:
12.[Bonham] shall be responsible to execute the work as
required regardless of the subgrade conditions. [Bonham]
understands that water tables and rock elevations vary
throughout the site and has satisfied themselves that they
understand and have accounted for these conditions within
their price. For the avoidance of doubt, there will be no
adjustment to price or schedule resulting from the existing
conditions.
A geotechnical report provided by Gadd which detailed the subsurface conditions,
also was furnished to Bonham for bidding purposes, along with project plans,
specifications and other information all of which was incorporated by reference into the
proposed subcontract. After visiting the jobsite and considering the contract documents,
Bohnam submitted a bid to Peart, and the parties executed the subcontract. Simultaneously,
Bonham entered into a written labor-only agreement with Hawkins, under which
Hawkins agreed to supply the equipment operators and laborers, while Bohnam supplied
the supervision, equipment, materials and all other items.
During performance of mass excavation, Hawkins and Bonham encountered a
substantial amount of rock which was not reflected in the geotechnical report and stopped
all excavation. Bonhams project manager reported the rock to Pearts project manager, as
Page 13
2024 Marvin Laws, P.C.
Case Studies
well as the fact that for all rock removed, a corresponding amount of select fill would be
necessary in light of the design. According to Bonham, Pearts project manager orally
instructed it to proceed with removal of the rock and import of structural fill but said
nothing extra would be paid on account of Section 12 of the subcontract, noted above. On
the other hand, Peart contended that it was not advised of the additional rock until after a
substantial amount of excavation had already occurred, which is the primary reason it
denied the claim, in addition to Section 12 of the subcontract. Neither party confirmed
these discussions in writing, and it is unknown if Peart advised Gadd of the situation.
Bonham proceeded with the rock removal and import of select fill, as required
under the contract documents. Afterward it proposed a change order for the actual costs of
$973,420, of which $322,530 was for Hawkins labor costs. Peart refused to sign the
change order, contending that Bonham took the risk first by signing the subcontract and
then by proceeding with the work in the absence of a written change order. After the work
was completed, Hawkins filed a lien against the project in the amount of $322,530. The
lien was discharged by Peart, who obtained a lien discharge bond from its surety and
provided the same to the county clerk in accordance with Oklahoma statutes. Hawkins then
sued Bonham under their labor-only agreement, but also sued Peart and Gadd for unjust
enrichment, as well as the lien discharge surety. Bonham asserted cross-claims against
Peart for breach of contract and against Gadd for unjust enrichment. Other than filing their
claims and defenses with the court, the parties otherwise did nothing in the lawsuit decided
instead to focus on mediating and settling the case, if possible.
Pearts contract with Gadd contained an indemnity provision under which Peart
was obligated to defend and indemnify Gadd from any losses suffered on account of the
Hawkins/Bonham claims. Presumably because of this, Gadd did not participate in the
mediation. Nevertheless, Peart, Hawkins and Bonham were able to reach a compromise
without Gadds involvement.
Page 14
2024 Marvin Laws, P.C.
Case Studies

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!