Question: CashflowProbabilityCashflow Probability 6 0 , 0 0 0 0 . 3 5 0 , 0 0 0 0 . 3 6 0 , 0 0

CashflowProbabilityCashflow Probability
60,0000.350,0000.3
60,0000.5
70,0000.2
80,0000.460,0000.3
80,0000.5
100,0000.2
100,0000.380,0000.3
100,0000.5
120,0000.2
The projects initial cash outlay is Sh 100,000 with a cost of capital of 12%. What is the projects expected monetary value (EMV)