Question: CATEL = a. True b. False Question 3 Not yet answered Marked out of 2.00 Flag question The design capacity for engine repair in our

CATEL = a. True b. False Question 3 Not yet

CATEL = a. True b. False Question 3 Not yet answered Marked out of 2.00 Flag question The design capacity for engine repair in our company is 50 trucks per day. The effective capacity is 30 engines per day and the actual output is 25 engines per day. The utilization and efficiency of the operation are: Select one: a. 50% and 83% respectively b. 50 % and 83.3 % respectively c 83.2% and 50% respectively d. none of these : O