Question: CCM ( Critical Chain Method ) focuses on Select one: a . Resources b . Tasks The Path is the sequence of activities in a

CCM (Critical Chain Method) focuses on
Select one:
a. Resources
b. Tasks
The Path is the sequence of activities in a network diagram that represents the longest path through the project, which determines the shortest possible duration.
A chart is a is a horizontal bar chart that provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project.
The Forward Pass through a network diagram identifies the for the activities in the diagram.
Select one:
a. Early Start and Early Finish times
b. Late Start and Late Finish times
is an estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
 CCM (Critical Chain Method) focuses on Select one: a. Resources b.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!