Question: CE 3 3 2 CONSTRUCTION ENGINEERING AND MANAGEMENT CLASSWORK BRIDGE CONSTRUCTION EXAMPLE table [ [ table [ [ Activity ] , [ Number
CE CONSTRUCTION ENGINEERING AND MANAGEMENT
CLASSWORK
BRIDGE CONSTRUCTION EXAMPLE
tabletableActivityNumberActivity Description,tableDurationweeksResource DemandSet up site,Excavate left abutment,ExcavatorExcavate left pier,ExcavatorExcavate right pier,ExcavatorExcavate right abutment,ExcavatorPiledriving to right pier,Foundations left abutment,Concrete team for foundationsFoundations left pier,Concrete team for foundationsFoundations right pier,Concrete team for foundationsFoundations right abutment,Concrete team for foundationsConcrete left abutment,Concrete team for abutments and piersConcrete left pier,Concrete team for abutments and piersConcrete right pier,Concrete team for abutments and piersConcrete right abutment,Concrete team for abutments and piersPlace beams left span,CranePlace beams centre span,CranePlace beams right span,CraneClear site,,
PART Construct a precedence diagram for bridge contruction assuming that there are unlimited resources: excavators, concrete teams for foundations, concrete teams for abutments and piers and crane teams. Thus, most of the activities can be carried out in parallel. Make necessary network calculations, indicate the Critical Path CP and calculate the project duration.
PART Construct a precedence diagram for bridge construction assuming that there are limited resources: excavator, concrete team for foundation, concrete team for abutments and piers and crane team. Thus, the succeeding activities should wait for completion of preceeding activities and most of the activities should be carried out in series. Make necessary network calculations, indicate the Critical Path and calculate the project duration.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
