Question: CE 3 8 2 Hydraulic and Hydrologic Engineering Homework # 9 ( 1 0 Points ) A residential subdivision of 8 0 0 homes will
CE
Hydraulic and Hydrologic Engineering
Homework # Points
A residential subdivision of homes will be constructed with sewer service. The subdivision data is as follows:
a Estimated average water demand is gallons percapitaday GPCD
b Residential density is persons per residential dwelling
c Peaking factor is
d Sewer discharge is of water demand
e Grade of the sewer line is
f Manning
g Available pipe sizes
Find the following:
a Size of the sewer such that the pipeline will flow less than full at peak demand.
b Flow velocity at peak discharge.
c Normal depth of flow.
Note: Show all your calculations.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock