There are many primary reasons and some secondary reasons for having contingency responses prepared in advance of a risk event. Of the following, which is least likely to be a benefit noted?
A It will keep the planning time down for initial efforts and thus reduce budget needs.
B The overall responses will likely address the risk event in entirety with cost, time, and scope considered.
The team will be able to act more quickly to events.
D It will allow the team to think clearly by defining responses in advance of a situation.