Question: Celtify III GE - - - 5 1 0 3 - ED 2 - SP - 2 0 2 3 [ Based on Project Management
Celtify III GEEDSPBased on Project Management Professional PMP Based on PMBOK
D Which of the following statements is not true regarding the relationship between project deliverables, delivery cadence, development approach, and project
life cycle?
A The project life cycle and phases should connect delivery of business and stakeholder value from the beginning to the end of the project.
B A project life cycle cannot include multiple development approaches and delivery cadences.
C The project life cycle phases should facilitate the development approach and delivery cadchase required.
D
These relationships can change during the project as feedback is received and new understandings are gained.
E There are no standard project life cycle phases. Project life cycles and phases are dependent on industry, organization, number of deliverables,
development approach, and delivery cadence.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock