Question: CF NPV = CF. + CF CEN + + ... + = CF = (1 + r) (1+r). (1+z) CF is the expected cash flow

CF NPV = CF. + CF CEN + + ... + = CF = (1 + r) (1+r)". (1+z) CF is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted WACC . When the firm is considering independent projects, if the project's NPV exceeds zero the firm should accept the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the highest positive NPV. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 260 310 Project A Project B -970 -970 620 220 305 240 410 760 What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ 299.82 What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $ If the projects were independent, which project(s) would be accepted? -Select- If the projects were mutually exclusive, which project(s) would be accepted
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
