Question: Ch 1 2 - Adaptive Practice 1 2 . 4 Internal Rate of Return When the net present value ( NPV ) of a project

Ch 12- Adaptive Practice
12.4 Internal Rate of Return
When the net present value (NPV) of a project is positive, its internal rate of return will be
less than the discount rate.
equal to the discount rate.
greater than the discount rate.
equal to zero.