Question: CH 11 Problem 14-20 (Algo) Calculate the processing load and available capacity for the stereo speaker subassembly. Twenty employees work the assembly process for 40.

CH 11 Problem 14-20 (Algo) Calculate the processing load and available capacity for the stereo speaker subassembly. Twenty employees work the assembly process for 40. hours each. (Round your processing load to 1 decimal place.) pictureClick here for the Excel Data File Book rint Part Name: Stereo Speaker Week 2 Week 3 Week 4 780 1,120 Week 5 Week 6 Week 1 1,010 Tences Week 7 930 Week 8 1.190 1,260 1,200 780 Processing Time = 40 minutes Planned order releases Processing load (hours) Available capacity (hours)