Question: Ch 8 Assignment - Project Scheduling with Resource Limitations NAME: DO NOT TVPE IN THE FILE. Print out the sheet and work the problem with
Ch 8 Assignment - Project Scheduling with Resource Limitations NAME: DO NOT TVPE IN THE FILE. Print out the sheet and work the problem with a dark pencil. Develop a resource schedule in the loading chart below using the parallel method. Place the appropriate resource quantities in the blue schedule table cells, Be sure to also update each period, showing the change in ES. LF and Slack by period in the appropriate yellow table cells. Answer the following question: What is the final order in which the activities are scheduled? Note: Activities A, B, C, E \& F use two of the resource skills, while D uses only 1. Three of the resource skills are available. Following are the heuristics to be used: (make sure not to violate network precedence relationships in your resource-constrained schedule)