Question: Ch.3 Slack Time for A-G thamks! Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table Activity Immediate Predecessor(s) Time (days) 3 A AD C G E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project = 31 days d) Slack time for each of the activities is: Slack Time Activity A 0 ABUDEEO C F 21 B 630562 w 10 12 edit: 0