Question: Changing the initial plan to eliminate the risk or condition is known as _ _ _ _ _ _ _ _ _ _ _ _

Changing the initial plan to eliminate the risk or condition is known as ____________ the risk.Question 3Answera.Retainingb.Escalatingc.Avoidingd.Transferringe.Mitigating