Question: Chapter 1 4 - Determining Project Progress and Results Classwork - Earned Value Management Use the following information to answer parts a through h .

Chapter 14- Determining Project Progress and Results
Classwork - Earned Value Management
Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?
PV=$500,000
EV=$350,000
AC=$550,000
BAC=$1,200,000
a. Schedule variance (SV)
b. Cost variance (CV)
c. Schedule performance index (SPI)
d. Cost performance index (CPI)
e. Estimate to complete (ETC-first method)
f. Estimate to complete (ETC-second method)
g. Estimate at completion (EAC)
h. To-complete performance index (TCPI)
 Chapter 14- Determining Project Progress and Results Classwork - Earned Value

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!