Question: Chapter 1 4 Team Assignment Consider the AON graph of the project shown below. The activity times are 3 , 4 , 2 , 5
Chapter Team Assignment
Consider the AON graph of the project shown below. The activity times are
and days for activities A through A respectively.
a What is the latest start time for each activity?