Question: Chapter 1 7 , problem 7 . Suppose it is now the end of the seventh day and that activities A and B have been

Chapter 17, problem 7.
Suppose it is now the end of the seventh day and that activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,6, and 7. Activities C and H are ready to begin. What is the probability of finishing the project by day 23?