Question: Chapter 1 7 , problem 7 . Suppose it is now the end of the seventh day and that activities A and B have been

Chapter 17, problem 7.
Suppose it is now the end of the seventh day and that activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,6, and 7. Activities C and H are ready to begin.
The partners have decided that shortening the project by two days would be beneficial, as long as it doesnt cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the part d table. Which activity should be crashed first?