Question: ( Chapter 1 9 Project Management ) A project consists of 4 activities: A , B , C and D . A is known to

(Chapter 19 Project Management) A project consists of 4 activities: A, B, C and D.A is known to take 5 days, while B takes 5 days 50% of the time and 8 days 50% of the time. Project C takes 4 days all the time. Project D takes 2 days half of the time. But, the other half of the time, it is delayed and takes 7 days. The project network with dependencies is shown below. Each scenario is equally likely to occur.