Chapter 10 Student Homework Navigation Finish attempt... Question 3 Not complete Marked out of 5.00 P Flag question Working With Variances From the following data, determine the total actual costs incurred for direct material, direct labor, and variable overhead. Standard Costs Variances $120,000 3,0000 Direct material Price variance Quantity variance Direct labor Rate variance 100,000 TL o 2288 Efficiency variance Variable overhead Spending variance Efficiency variance Actual Costs Direct material Direct labor Variable overhead $ Check Previous Save Answers Next >