Question: Chapter 13 Saved Help Save & Exit Submi Check my work 2. The following table lists the components needed to assemble an end item, lead

Chapter 13 Saved Help Save & Exit Submi Check my work 2. The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. 5 Amount Lead Time points on Hand Item End 1 0 L 1 7 Direct Components L(2), C(1), K(3) B(2), J(3) G(2), B(2) H(4), B(2) K 2 2 1 18 23 31 28 B eBook J 2 G 2 4 H 2 0 100 Hint Click here for the Excel Data File Print a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 14. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan.) The latest week