Question: Chapter 14 JIT / Lean A production system uses kanban cards to control production and movement of parts. One work centre uses an average of
Chapter 14 JIT / Lean
A production system uses kanban cards to control production and movement of parts. One work centre uses an average of 40 pieces per hour of a certain part. Standard containers hold 10 parts. The waiting time for parts containers is about 36 minutes. Management has assigned a safety factor of .20 to this work centre. How many containers should be used to support this operation? (4 marks)