Question: Chapter 14 JIT / Lean A production system uses kanban cards to control production and movement of parts. One work centre uses an average of

Chapter 14 JIT / Lean

A production system uses kanban cards to control production and movement of parts. One work centre uses an average of 40 pieces per hour of a certain part. Standard containers hold 10 parts. The waiting time for parts containers is about 36 minutes. Management has assigned a safety factor of .20 to this work centre. How many containers should be used to support this operation? (4 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!