Question: Chapter 14, question 5: Using the information in Problem 14.5, construct a net material requirements plan using the following on-hand inventory. ITEM ON-HAND INVENTORY ITEM
Chapter 14, question 5: Using the information in Problem 14.5, construct a net material requirements plan using the following on-hand inventory.
| ITEM | ON-HAND INVENTORY | ITEM | ON-HAND INVENTORY |
| S | 20 | W | 30 |
| T | 20 | X | 25 |
| U | 40 | Y | 240 |
| V | 30 | Z | 40 |
Note: Fill out the following table to answer this question:
Item Z has an order release of 320 units in week 3.
Item Z has an order release of 320 units in week 1.
Item Z has an order release of 320 units in week 2.
Item Z has an order release of 60 units in week 3.
Item Z has an order release of 300 units in week 2.
Chapter 14, question 7: Refer again to Problems 14.5 and 14.7. In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect this change.
Item Z has an order release of 300 units in week 2 and an order release of 60 in week 3.
Item Z has an order release of 300 units in week 2 and an order release of 320 in week 3.
Item Z has an order release of 60 units in week 2 and an order release of 320 in week 3.
Item Z has an order release of 320 units in week 2 and an order release of 300 in week 3.
Item Z has an order release of 320 units in week 2 and an order release of 60 in week 3.