Question: Chapter 15 homework Gantt Chart Ron is reviewing the chart at the end of the 7 th day. All jobs start at the beginning of

Chapter 15 homework

Gantt Chart

Ron is reviewing the chart at the end of the 7th day. All jobs start at the beginning of a day and end at the end of a day unless otherwise stated. The following jobs must be recorded:

Job 151 was scheduled to start on day 3 and take 6 days. It is 1 day ahead of schedule now.

Job 177 was scheduled to start on day 1 and take 4 days. It is on time.

Job 179 was scheduled to start on day 7 and take 2 days. It got started a day early and is on schedule to finish on day 8.

Job 211 was scheduled to start on day 5 but got delayed until day 6. It should take 3 days and is on time.

Job 215 started on day 4 and should take 5 days. It is behind by 2 days.

Assignment Method

Use the assignment method on the following information to minimize costs.

Marketing Finance Operations HR

Chris 80 120 125 140

Steve 20 115 145 160

Juana 40 100 85 45

Rebecca 65 35 25 75

Sequencing

Today is day 275 and the jobs below arrived in the order A through E on day 275.

Job Due Date Duration

A 313 8

B 312 16

C 325 40

D 314 5

E 314 3

Consider FCFS, SPT, LPT, EDD, and the critical ratio. Which one is best?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!