Question: Chapter 18 Part A: Delta Corp contracted to construct a tower for a contract price of $2,000,000. Construction began in 2023 and was completed in

Chapter 18 Part A: Delta Corp contracted to construct a tower for a contract price of $2,000,000. Construction began in 2023 and was completed in 2025. Selected data related to the contract follows: 2023 2024 2025 Costs incurred during the year $300,000 $825,000 $370,000 Estimated costs to complete 900,000 281,250 Billings during the year 375,000 830,000 795,000 Collections during the year 310,000 850,000 840,000 Required: Calculate the amount of revenue, expenses and gross profit reported each year for each of the following methods: (Part A) Percentage of Completion (Part B) Completed Contract (Part C) Cost Recovery