Question: Chapter 3 : Applying Excel 2 3 Data 4 Allocation base 5 Estimated manufacturing overhead cost 6 Estimated total amount of the allocation base 7

Chapter 3: Applying Excel
2
3
Data
4 Allocation base
5 Estimated manufacturing overhead cost
6 Estimated total amount of the allocation base
7 Actual manufacturing overhead cost
Actual total amount of the allocation base
Machine-hours
$300,000
75,000 machine-hours
$290,000
68,000 machine-hours
9
10 Enter a formula into each of the cells marked with a ? below
11
12 Computation of the predetermined overhead rate
13 Estimated manufacturing overhead cost
14 Estimated total amount of the allocation base
15 Predetermined overhead rate
16
17 Computation of underapplied or overapplied manufacturing overhead
18 Actual manufacturing overhead cost
19 Manufacturing overhead cost applied to Work in Process during the year:
20
Predetermined overhead rate
21
Actual total amount of the allocation base
22
Manufacturing overhead applied
23 Underapplied (overapplied) manufacturing overhead
24
?
? machine-hours ? per machine-hour
?
? per machine-hour ? machine-hours
?
?
Required:
1. Check your worksheet by changing the estimated total amount of the allocation base in the Data area to 60,000 machine hours, keeping all of the other data the same as in the original example. If your worksheet is operating properly, the predetermined overhead rate should now be $5.00 per machine-hour. If you do not get this answer, find the errors in your worksheet and correct them.
How much is the underapplied (overapplied) manufacturing overhead? Did it change? Why or why not?
2. Determine the underapplied (overapplied) manufacturing overhead for a different company with the following data:
Allocation base
Estimated manufacturing overhead cost
Estimated total amount of the allocation base
Actual manufacturing overhead cost
Actual total amount of the allocation base
Machine-hours
$100,000
50,000 machine-hours
$90,000
40,000 machine-hours
3. What happens to the underapplied (overapplied) manufacturing overhead from part (2) if the estimated total amount of the allocation base is changed to 40,000 machine-hours and everything else remains the same? Why is the amount of underapplied (overapplied) manufacturing overhead different from part (2)?
4. Change the estimated total amount of the allocation base back to 50,000 machine-hours so that the data look exactly like they did in part
(2). Now change the actual manufacturing overhead cost to $100,000. What is the underapplied (overapplied) manufacturing overhead now? Why is the amount of underapplied (overapplied manufacturing overhead different from part (2)?5 Total Manufacturing Cost ADDED to Work-in-Process
8 ACTUAL Manufacturing Overhead Incurred
9 Manufacturing Overhead is Over or Under Applied
By how much
complete the excel spreadsheet please.
 Chapter 3: Applying Excel 2 3 Data 4 Allocation base 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!