Question: Chapter 4 Homework Saved 6 1 points Rand Company computed the following activity rates using activity-based costing Activity Activity Rate Setup $ 1,168 per setup
Chapter 4 Homework Saved 6 1 points Rand Company computed the following activity rates using activity-based costing Activity Activity Rate Setup $ 1,168 per setup Materials handling $ 60 per materials requisition Inspection $ 3 per unit inspected The company's deluxe model used the following activities to produce 2,000 units. Activity Actual Activity Usage Setup 2 setups Materials handling 25 materials requisitions Inspection 2,000 units inspected Compute the overhead cost per unit for the deluxe model using activity-based costing. eBook Ask Print Activity Usage Activity Rate Allocated Cost o References Activity Setup Materials handling Inspection Total allocated cost Units produced Overhead cost per unit