Question: Chapter 5 Estimating Project Times and Costs 1 6 3 management estimate; this represented about a 2 0 percent overrun! Furthermore, the bottom - up
Chapter Estimating Project Times and Costs
management estimate; this represented about a percent overrun! Furthermore, the bottomup time estimate based on the project network was four months longer than the top management time estimate. Another meeting was scheduled with the significant stakeholders to check the estimates and to brainstorm for alternative solutions. At this meeting everyone agreed the bottomup cost and time estimates appeared to be accurate. Following are some of the suggestions from the brainstorming session.
Change scope.
Outsource technology design.
Use the priority matrix found in Chapter to get top management to clarify their priorities.
Partner with another organization or build a research consortium to share costs and to share the newly developed technology and production methods.
Cancel the project.
Commission a breakeven study for the laser printer.
Very little in the way of concrete savings was identified, although there was consensus that time could be compressed to the market launch date, but at additional costs.
Lauren met with the marketing Connor production Kim and design Gage managers, who yielded some ideas for cutting costs, but nothing significant enough to have a large impact. Gage remarked, "I wouldn't want to be the one to deliver the message to top management that their cost estimate is $ off! Good luck, Lauren."
At this point, what would you do if you were the project manager?
Was top management acting correctly in developing an estimate?
What estimating techniques should be used for a missioncritical project such as this?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
