Question: Chapter 5 Exercise First Name: ____________ Last Name: ___________________ 1. The R&D department is planning to bid on a large project for the development of
Chapter 5 Exercise
First Name: ____________ Last Name: ___________________
1. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:
|
|
|
|
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | - | 3 |
| B | A | 5 |
| C | A | 4 |
| D | A | 4 |
| E | B | 4 |
| F | C, D | 4 |
| G | D, F | 7 |
| H | D | 4 |
| I | E, G, H | 8 |
- What is the critical path?
- What is the early start, early finish, late start, late finish of each activity?
- What is the slack of each activity?