Question: Chapter 6: A company is setting up an assembly line to produce 30 units per hour. The table below identifies the work elements, times, and
Chapter 6: A company is setting up an assembly line to produce 30 units per hour. The table below identifies the work elements, times, and immediate predecessors.
| Work Element | Time (Sec.) | Immediate Predecessor(s) |
| A | 40 | - |
| B | 46 | A |
| C | 20 | B |
| D | 34 | B |
| E | 40 | B |
| F | 30 | C |
| G | 45 | D |
| H | 35 | F,G |
| I | 25 | E |
| J | 45 | H,I |
a. What cycle time is required to satisfy the required output?
b. What is the theoretical minimum number of stations?
c. Use one of the heuristic decision rules described in Table 6.3 on page 235 to balance the assembly line so that it will produce 30 units per hour. Clearly state the decision rule you use and complete the below table using the selected rule.
Note: The actual number of stations to be used to balance the line depends on the heuristic decision rule used and may be higher than the theoretical minimum calculated in part b.
| Decision Rule: |
| ||||
|
|
|
| Work Element | Cumulative | Idle Time |
| Station | Candidate(s) | Choice | Time (sec) | Time (sec) | (c = ? sec) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d. What is the efficiency of the line you found in part c?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts